The problem
Hourly production counts were written up by each line supervisor and added together later. By the time anyone saw that a line had fallen behind or that defects were climbing, the day's output was already lost.
What we did
- 01
Built one workbook where supervisors enter hourly output per line, and everything else (target hit, efficiency, quality pass rate) is calculated from it.
- 02
Each line gets a status set by formula: on target, watch, below, or on changeover, so the floor manager sees problems at a glance.
- 03
Added the day's summary at the top, an output-by-hour chart and a defects (DHU) sheet for quality follow-up.
The outcome
Delivered and in use. The screen shown is the workbook's layout with sample figures; the client's production data stays private.